Bid Item 8– Reservoir Finishes Associated with Seismic Retrofit Construction
Lump sum price shown shall cover the complete cost of providing all materials, equipment and labor necessary for painting and coating the reservoir interior and exterior surfaces that are impacted by the structural improvements associated with the seismic retrofit construction including: bottom 6-feet of reservoir shell (interior and exterior), reservoir floor. Payment shall be lump sum. 18 of 134 9/6/2016 VIE Consul

Bid  6 ft up and floor  Inside   Exterior 6 ft high

tank 36 total

 BID SCHEDULE:
Items Added:  seperet line pricing  compleate  exterior 
A2 Reservoir Finishes-Poly Urethane Coating (Series 73)
 This Bid Item was added as an alternate to protect the Tnemec
coating on the exterior of the tank. Item includes top of tank.  
clear coat

 

A2 Reservoir Finishes-Poly Urethane Coatings (Series 73)no 73
 Specification called out coating that cannot be applied in Weber
County. The specification has been revised for a coating that can
be applied.

Bid Item 9 – Reservoir Finishes NOT Associated with Seismic Retrofit Construction
Lump sum price shown shall cover the complete cost of providing all materials, equipment and labor necessary for painting and coating the reservoir interior and exterior surfaces that are not impacted by the seismic retrofit construction including: reservoir shell above the 6-foot elevation (interior and exterior), reservoir roof (interior and exterior). Payment shall be lump sum.

30 ft high  Paint   and 30 exterior outside 
and roof  inside and out side 

Here you go Bob   Blake Sent
1. Interior floor and 6' up walls
1,144sqft sandblast near white metal and apply coatings per specifications 

2. Interior shell 2,639 sqft 
Sandblast and apply coatings

3. Interior roof 800 sqft
Sandblast and apply coatings 

4. Exterior shell plus top of tank 
3,167 sqft
Hydroblast and apply coatings per specifications

5. 6' up the exterior walls 538 sqft 
Hydroblast and apply coatings as per specifications 
 Weber Basin logo to be applied 
Welding and testing reservoir anchors 
This the best I can do now back to school